Construction and engineering / 05
Construction plan and scope review
The cheapest thing you can buy from us, and usually the most useful. Before anybody prices a set, somebody reads all of it and tells you whether it is complete enough to price.
Why this exists as a separate service
A bid set is assumed to be complete until somebody proves otherwise, and nobody has time to prove otherwise in bid week. So the gaps get discovered during pricing, or after award, which is the expensive end.
A plan and scope review is a small fee to find out what you are dealing with. If the set is clean, you have lost very little. If it is not, you have found out before you committed a number to it.
What a review produces
- A page by page index
- Every sheet in the set, with its discipline and what it actually contains. Not the drawing list, the file.
- Sheet reconciliation
- The file checked against its own drawing list, both ways. Sheets listed and missing, and sheets present but not on the list.
- Missing sheet identification
- Named, by sheet number and discipline, so you can request them specifically rather than asking for a complete set again.
- Conflict flagging
- Where the set contradicts itself, with both sides of the contradiction cited and a note on what it changes.
- Scope extraction
- What the documents actually ask for, separated from what they cannot yet tell you.
- Bid or no bid input
- An honest statement of how complete the documents are, so you can decide whether the job is worth your bid effort.
What has actually been found on real sets
These are real findings from real reviewed sets, with the projects and clients removed. Nothing in this list is illustrative.
- Mechanical, sprinkler and power sheets named on the drawing list and absent from the issued file.
- The same sheet number used twice, on two different drawings, in one set.
- Two conflicting occupancy classifications stated in the same package, which changes egress, rating and sprinkler scope.
- Two different code cycles cited in one set, so which edition governs was genuinely unclear.
- An elevator count on the drawings that contradicted what the client believed was in the building.
- A wall assembly sheet referenced by keynote and not present in the set, so the rated assemblies could not be priced from the documents supplied.
- A graphic scale bar printed at double the sheet’s actual scale, which would have doubled every quantity taken from it.
- A 592 sheet package spanning two companion contracts, where the scope in question sat across both and neither set was complete on its own.
Questions contractors actually ask
How long does a review take?
It depends on the size of the set, and we quote a turnaround with the fee before starting. A review is always faster than an estimate, because it is a read and reconcile exercise rather than a measurement exercise.
Will you tell me not to bid?
If the documents are not complete enough to price responsibly, yes, and we will say why. That is worth more to you than a number built on a set with holes in it.
Can the review roll into an estimate?
Yes, and it usually should. The review is the first step of every estimate we do anyway. Buying it separately just means you see the findings before you commit to the pricing work.
Work of this kind
- Construction
New four storey multiple dwelling
Brooklyn, New York
A 97 page set reviewed page by page. Missing sheets, code conflicts and an elevator count discrepancy identified before pricing.
Plan & Scope Review
Read the case study - Construction
University physical education building, pool scope
Upstate New York
Pool decommissioning and infill scope identified across two companion contracts. A 592 sheet set reconciled before any pricing.
Plan & Scope Review
Not ready to send a full set for pricing?
A plan review is the small first step. You find out what you are dealing with before committing to the estimating work.