Estimating practice / 8 min read

The scope items that lose bids, trade by trade

Bids are rarely lost on the big quantity. They are lost on the item nobody carried, because it was described in a specification paragraph rather than drawn on a plan.

There is a pattern to the items that get missed. Almost none of them are hidden. They are simply somewhere other than where a takeoff naturally looks: in a specification section, in a wall section detail, in a schedule, or in a narrative paragraph that describes work the drawings never show.

What follows is a catalogue by trade. It is drawn from real reviewed and priced sets, with the projects removed. If you are bidding one of these trades this week, it is a checklist.

Acoustical ceilings

Perimeter angle taken as a room perimeter
The angle runs around every column, every soffit return and every interior island, not just the walls. A field full of columns understates by a lot.
Seismic bracing
Compression posts and splay wire sets come from the seismic design category and the ceiling area, both of which live in the specification rather than on the reflected ceiling plan.
Cutouts counted as one number
A troffer drop in and a slot diffuser cut are not the same labour. Count them by fixture type.

Interior demolition

Casework and store fixtures
The most commonly missed item on this trade. Millwork, wall standards and display units are almost never in the demolition drawing scope, and they are always in the building. They come off the photographic survey.
Column wraps
Individually counted, often furred with more than one layer, and invisible on a floor plan read as areas.
Make safe against removal
Sets frequently describe both for the mechanical and electrical scope without drawing the boundary. Getting it wrong in either direction is expensive.
Disposal priced by volume
Haul and tip are charged by weight. Converting to tonnage by material type, then applying the diversion requirement, is part of the takeoff rather than an afterthought.

Concrete restoration

Traffic coating reinstatement
Coating is removed to repair and reinstated afterwards over an area always larger than the patch. On a full deck it is a substantial square footage and it belongs on its own line.
Expansion joints bundled with sealant
Different product, different crew, materially higher unit rate. One of the most common register errors.
Shoring
Implied by the extent of full depth work on suspended slabs and almost never a line in the repair register.
Partial and full depth on one line
Full depth on a suspended slab pulls shoring, formwork from below and a longer closure. It is not a deeper version of a surface patch.

Drywall

Shaftwall at stair and elevator landings
A different product and a different install, appearing as one line on a partition schedule and adding up fast in a stair core.
Metal stud bulkheads and soffits
Neither wall nor ceiling, slow, detail heavy, and invisible on a plan read as partition lines.
Firestopping and head of wall
Every rated wall has a head of wall condition and every penetration a listed detail. It is priced work.
Backing and blocking
Behind every wall mounted item, and usually an architectural note rather than part of the drywall scope drawings.

Masonry and earthwork

Grout fill condition
Fully grouted and partially grouted walls look identical in elevation and are very different prices. It comes from the structural drawings.
Cavity components
Through wall flashing, weeps, anchors and insulation live in the wall section detail, not on the plan.
Over excavation and recompaction
Called for in the geotechnical report rather than on the grading plan, which is exactly why it is missed. It can be a very large volume.
Topsoil strip and respread
Two operations with a stockpile in between, and stockpile space is a site constraint before it is a cost.