A utility run is priced per foot, and the price per foot changes sharply with depth. A plan that shows the run without the profile is half a drawing.
What we measure, and in what units
- LF pipe by size and depth band
- EA structures by type
- EA connections to existing
- CY bedding and backfill
- SF surface restoration
What the deliverable looks like for this division
Pipe by size along the plan and by depth from the profile, banded because the trench, the shoring and the productivity all change with depth. Structures and connections counted, bedding and backfill by volume, and the surface restoration behind every connection as its own scope.
Scope items routinely missed on this division
Only someone who has priced the work knows what falls through the gaps. No competitor publishes this list.
- Trench depth bands, since the price per foot changes sharply with depth and a single rate across the run is wrong somewhere.
- Connection to existing, and the surface restoration behind it, which can be the largest item on a short run.
- Bioretention and storm treatment structures as their own scopes with their own media and plantings.
- Testing, flushing and disinfection of new mains.
Documents needed to price it
- Utility plans and profiles
- Civil details and the jurisdiction’s standard plans
- The soils report
- The Division 33 specifications
Questions people in this trade actually ask
Why band by depth?
Because a foot of pipe at three feet and a foot at nine feet are different trenches, different shoring and different crews. One rate across both under prices the deep end and over prices the shallow.
Work of this kind
- Construction
Express car wash, new build
Southern California
Grading, concrete, storm drain and bioretention, sanitary sewer, landscape, site lighting and alley reconstruction. Seven scopes consolidated into one proposal.
Estimating & Takeoff / Bid & Proposal Support
The service behind this
Estimating & TakeoffRelated divisions
Bidding Division 33 work?
Send the documents and the bid date. A written fee and turnaround come back before anything is measured.