A masonry wall is five or six trades stacked in one line item. Price it as a square footage of wall and the reinforcing, the grout and the lintels disappear into an assumption.
What we measure, and in what units
- EA CMU and brick by size and type
- CY grout by fill condition
- TON reinforcing, vertical and horizontal
- SF veneer with the backup identified
- EA lintels by type and span
- LF flashing, EA weeps, EA anchors
What the deliverable looks like for this division
Units by size and type including bond beam, lintel block and specials. Vertical bar by cell spacing, horizontal joint reinforcement by run. Grout by whether the wall is fully grouted, partially grouted at reinforced cells or ungrouted, which is one of the largest swings in the price and invisible on an elevation.
Scope items routinely missed on this division
Only someone who has priced the work knows what falls through the gaps. No competitor publishes this list.
- Reinforcing and grout in cells, which is a volume and not an area. Fully and partially grouted walls look identical in elevation and are very different prices.
- Lintels, bearing and veneer anchors, each a count from the schedule and the wall section rather than the plan.
- Cavity components: flashing in linear feet, weeps by count, insulation and air barrier by area. They live in the wall section detail.
- Scaffold and access above a single storey, priced from the elevation and the sequence rather than the wall area.
Documents needed to price it
- Architectural elevations and plans
- Structural drawings with reinforcing size, spacing and grout requirements
- Wall sections and typical details
- The masonry specification, for unit types, mortar and grout
- The lintel and opening schedules
Questions people in this trade actually ask
Do you separate the grout from the block?
Always, with the fill condition stated per wall type.
Can you do a Division 04 scope only?
Yes. That is the normal case for this trade and it is what has been delivered.
Work of this kind
- Construction
High school fitness centre addition
Westchester County, New York
Division 04 masonry estimate with colour coded markup overlays.
Estimating & Takeoff
The service behind this
Estimating & TakeoffRelated divisions
Bidding Division 04 work?
Send the documents and the bid date. A written fee and turnaround come back before anything is measured.